- harbour and service
- 850+ berths
- staying

– Preloading on the camper site for the new crane track, takes 3 months
– Moving the barrier on Hemmeland to its final location
– New fence around our plot on Hemmeland
– Piling work for the supermarket and the first block of houses until August (Project – finished)
– Breakwater installed
– Optimist storage moved to the Roundabout
– Crane track finalized
– Glassfiber connection moved, new water connection
– Moved the capacity of our electricity connection
– All jetties are removed so the harbour is ready for the new ones
– All new jetties are in Monnickendam and connected
– Arrival of new crane (early March)
– Finalising the renovation of the harbour building including a new sewer
– Building the wharf (hardening of the terrain)
– Construction of the new workshop
– Opening of the toilet building – During the renovation, restrooms will be available at De Ark. Showers are available at the Waterland location.
– Lauch of the winter storage
– Prepare the ground of the new yard
– All boats at their (new) berth
Last month of the Waterland location. The demolition will start end of May.