20-5-2025 – Planning a move like ours has many facets. In addition to the planning of the Gouwhaven project, there is the “normal” port season (booking winter storage is possible from 1 July) and our own construction activities. Below we indicate the expected activities per month and between brackets we’ve updated the items on latest status:

June 2025

– Preloading on the camper site for the new crane track, takes 3 months (Our works – started)
– Moving the barrier on Hemmeland to its final location (Our works – finished)
– New fence around our plot on Hemmeland (Our works – finished)
– Piling work for the supermarket and the first block of houses until August (Project – finished)

July 2025

– Register for winter storage, you will receive the information in the last week of June (You – both locations are fully booked)
– Pre-loading on the camper site for the new crane track, 2 months left (Our works – started)
– Piling work for the supermarket and the first block of houses until August (Project – finished)

August 2025

– Last month of pre-loading of camper site for the new crane track (Our works)
– Last month of piling work for the supermarket and the first block of houses (Project – finished)
– After summer holidays: deconstruction the I- and the rigging jetty at Hemmeland (Project – started)
– After summer holidays: start of preparations for the renovation of the harbour building (Our works – started)
– After summer holidays: start of the construction of the breakwater (Our works – started)

September 2025

– Start of construction of crane track (Our works – started)
– Breakwater ready (Our works – planned for last week of September)
– Renovation of harbour office (Our works – started) – during the works there are toilets available. Showers are open at the Waterland location.

October 2025

– Last month of construction of crane track (Our works)
– Renovation of the harbour office (Our works)

November 2025 – April 2026

– Arrival of new crane (Our works)
– Delivery of harbour building (Our works)
– Construction of the new workshop (Our works)
– Boats are on the shore or at Waterland JKL or Hemmeland A&B (Our works and you)
– Jetties C to G and C to H are being removed
New jetties will be installed in the winter and we will connect them

May 2026

Last month of the Waterland location. The demolition will start end of May.

How can we help?

waterland team