20-5-2025 – Planning a move like ours has many facets. In addition to the planning of the Gouwhaven project, there is the “normal” port season (booking winter storage is possible from 1 July) and our own construction activities. Below we indicate the expected activities per month and between brackets we’ve updated the items on latest status:

Realized June – October 2025

– Preloading on the camper site for the new crane track, takes 3 months
– Moving the barrier on Hemmeland to its final location
– New fence around our plot on Hemmeland
– Piling work for the supermarket and the first block of houses until August (Project – finished)
Breakwater installed
– Optimist storage moved to the Roundabout

November 2025

– Build the new crane track (We)
– Renovation of the toilet building (We, started in September) – During the renovation, restrooms will be available at De Ark. Showers are available at the Waterland location.
– Demolition of the jetty begins, starting at Hemmeland I. Boats must be in their winter moorings by November 11th. The connecting jetty will be removed (We)

December 2025 – April 2026

– Arrival of new crane (Our works)
– Delivery of harbour building (Our works)
– Construction of the new workshop (Our works)
– Boats are on the shore or at Waterland JKL or Hemmeland A&B (Our works and you)
– Jetties C to G and C to H are being removed
New jetties will be installed in the winter and we will connect them

May 2026

Last month of the Waterland location. The demolition will start end of May.

How can we help?

waterland team